Project Detail

Data updated on: 5/07/2012 10:57AM Print This Page
Project Summary
Project ID 348702007 TxDOT District Tyler County Name Smith Funding Status Funded
Highway LP 49 Project Length 2.485 Miles Project Type Proposition 14 Bid Date 2009-Dec
Work From 0.294 MI W OF FM 756, NE Low Bid Amount $15,681,180.11
Work To 0.266 MI W OF SH 110
Description CONSTRUCT NEW TOLLROAD
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company LONGVIEW BRIDGE AND ROAD, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/25/2010 02/16/2010 608 572 87.73 % 88.04 %
 
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $768,377.83 $541,190.64
Construction $15,801,395.66 $15,065,302.52
Construction EngineeringConstruction Engineering Definition $705,653.10 $589,323.13
Contingency Contingency Definition $1,019,276.71  
Indirect Indirect Definition $972,233.17  
Total Cost $19,266,936.47 $16,195,816.29