Project Detail
Return to: Report List or Main Query Page

| Project Summary |
| Project ID |
348701004 |
TxDOT District |
Tyler |
County Name |
Smith |
Funding Status |
Funded |
| Highway |
LP 49 |
Project Length |
6.569 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2009-Jun |
| Work From |
.11 M N OF SH 31(2 M E OF FM 2661)S |
Low Bid Amount |
$37,870,805.05 |
| Work To |
.53 M S OF SH 155(2 M N OF FM 2868) |
| Description |
CONSTRUCT NEW TOLLROAD |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Vernon Webb, P.E. |
Phone: |
(903) 510-9296 |
| Construction Company |
LONGVIEW BRIDGE AND ROAD, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2006 |
08/2007 |
01/2009 |
04/2009 |
04/2009 |
04/2009 |
10/2006 |
04/2009 |
| Actual Date |
08/2006 |
08/2007 |
01/2009 |
04/2009 |
04/2009 |
04/2009 |
10/2006 |
04/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 07/21/2009 |
08/06/2009 |
812 |
703 |
86.58 % |
88.43 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$2,229,614.47 |
$1,756,007.30 |
| Construction |
$57,923,519.99 |
$36,777,416.62 |
Construction Engineering |
$1,940,484.33 |
$1,662,526.91 |
Contingency
 |
$3,697,768.75 |
|
Indirect
 |
$2,420,724.28 |
|
| Total Cost |
$68,212,111.82 |
$40,195,950.83 |
| |
- Construction cost is the amount on this project that is either completely or partially paid through Economic Stimulus funding |
|
 |